Project Manager / Construction Manager

Detail-oriented Civil Engineer with 36 years of experience in managing different phases of engineering operations. Seeking to work as Projects Manager/ Construction Manager Position in a construction company to utilize my extensive experience with construction procedures and leadership. Enthusiastic construction professional with expertise in managing construction budgets and developing project goals. Ready to expand my skill set and practical construction experience to offer the highest quality of services with a complete focus on safety, environmental, and health issues.

Overview

37
37
years of professional experience
6
6
years of post-secondary education

Work history

Projects Manager

Tamcon Contracting Company
Al Hidd, Bahrain
08.2022 - Current
  • Company Overview: AA Grade, ISO 9001,45001, 14001.

1. 2022-2025

  • Project: Construction of 4 Storey Office Building at Jebel for Bapco Upstream (Oil & Gas field Area)
  • Client: Bapco Upstream (Tatweer Petroleum)
  • Consultant: Bapco Upstream, Kooheji Engineering
  • Project cost: 2 million

2. 2023 -2025

  • Position: Project Manager
  • Project: Reverse Osmosis Brackish Water Treatment Plant at Hidd
  • Client: Bahrain Investment Wharf (BIW)
  • Consultant: WRD (Bahrain Govt
  • Water Resource Department, Adel Ahmadi Associates)
  • Project Cost: 1 million
  • Position: Project Manager

3. 2023 -2024

  • Project - 2 Nos 5 Storey Accommodation Building at Hidd.
  • Client Bahrain Investment Warf
  • Consultant : Madaen Engineering
  • Project cost : 2.million
  • Position : Project Manager



Projects Manager

Mohammed Jalal Contracting Company
Manama, Bahrain
01.2006 - 01.2022
  • Company Overview: AA Grade, ISO 9001

1. 2022-2022

  • Project: Walm Royal Lodge for Royal Court
  • Consultant: MSCEB
  • (Mohammed Salahuddin Consulting Engineering Bureau)
  • Project cost: 2 million
  • Position: Projects Manager

2. 2021-2022

  • Project: Luxury Villa at Wasmiya for the Ruling Family
  • Consultant: MSCEB
  • Project cost: 5 million
  • Position: Project Manager

3. 2021 -2022

  • Project: Interior Fit out works for BSE. (Bahrain Society of Engineers )
  • Consultant: DTEB
  • Project Cost: 1. million

4. 2020-2021

  • Project: Water Factory & Kitchen Building
  • Consultant: The Modern Architect
  • Project cost: 3 million
  • Position: Projects Manager

5. 2018 -2020

  • Project: 3 Nos Luxury villas at Riffa
  • Consultant: MSCEB
  • Project cost: 9 million
  • Position: Projects Manager

6. 2017-2018

  • Project: Car Park Building at Adliya
  • Consultant: Adel Ahmadi Associates
  • Project cost: 4 million
  • Position: Projects Manager

7. 2016-2017

  • Project: 11 Nos Ammunition Store for BDF
  • Consultant: BDF
  • Project cost: 3 million
  • Position: Projects Manager

8. 2015-2016

  • Project: 3 Nos Hanger at Shaikh Isa Airbase
  • Consultant: BDF
  • Project cost: 3 million
  • Position: Projects Manager

9. 2014-2015

  • Project: 2 Nos Accommodation for National Guard
  • Consultant: Bahrain National Guard
  • Project cost: 2 million
  • Position: Projects Manager

10. 2013-2014

  • Project : Air Fuel Depot for Sakhir Airbase.
  • Client : Royal Court
  • Consultant - BDF
  • Project cost : 1. million
  • Position : Project Manager.

11. 2012-2013

  • Project : BBK Mall at West Riffa
  • Client : Bank of Bahrain & Kuwait
  • Consultant : MSCEB
  • Project cost : 3. million
  • Position : Project Manager

12. 2011 - 2012

  • Project: Refurbishment works to Gulf Air VIP Lounge
  • Consultant: Gulf Air
  • Project cost: 1.5 million
  • Position: Projects Manager

13. 2011 -2012

  • Project: 42 Nos Villas at Hamala
  • Consultant: Ministry of Housing
  • Project cost: 2 million
  • Position: Projects Manager

14. 2010 -2011

  • Project : Interior Fit out works for Sash Spa at Riffa
  • Client : Ruling Family
  • Consultant : MEEB, IDA
  • Project cost : 1 million
  • Position : Project Manager

15. 2010 -2011

  • Project: Extension to BMMI store at Sitra
  • Consultant: Middle East Engineering
  • Project cost: 1.5 million
  • Position: Projects Manager

16. 2009 - 2010

  • Project: Office Building at GPIC
  • Consultant : GPIC
  • Project cost : 0.5 million
  • Position: Projects Manager

17. 2008 - 2009

  • Project: Royal Pavilion & Gate at Sakhir Airbase.
  • Consultant: BDF
  • Project cost: 2 million
  • Position: Projects Manager

18. 2007 -2008

  • Project: Royal Hangar at Sakhir
  • Client : Royal Court
  • Consultant: BDF
  • Project cost: 8 million
  • Position: Projects Manager

19. 2006 -2007

  • Project: Extension to Thai restaurant Gulf Hotel
  • Consultant: IKA
  • Project cost: 1 million
  • Position: Projects Manager.

Project Engineer, Site Manager

Hameed Alnooh Constructions
Manama, Bahrain
01.1988 - 01.2006
  • Company Overview: B Grade

1. 2005 -2006

  • Project: Building for Universal Lighting
  • Consultant: MSCEB
  • Project cost: 1.5 million
  • Position: Site Manager

2. 2004 - 2005.

  • Project: MS Centre at Seef
  • Consultant: MSCEB
  • Project cost: 1.5 million
  • Position: Site Manager

3. 2003 -2004

  • Project: AL Hassan Fuel station at Muharraq
  • Consultant: MSCEB
  • Project cost: 1 million
  • Position: Site Manager

4. 2002 -2003

  • Project: Yateem Filling Station Manama
  • Consultant: MSCEB
  • Project cost: 0.75 million
  • Position: Site Manager

5. 2001 -2002

  • Project: Ruben store at Salmabad
  • Consultant: MSCEB
  • Project cost: 1.5 million
  • Position: Site Manager

6. 2000-2021

  • Project: 28 Nos of Town Houses
  • Consultant: MOH
  • Project cost: 1 million
  • Position: Site Manager

7. 1999 -2000

  • Project : Private Villa at Mahoose
  • Client : Mr.Adel Al Maskati
  • Consultant : Modern Architect.
  • Position : Project engineer.

8. 1998 -1999

  • Project : 8 Storey Building at Juffair
  • Client : Mr. Abbas Al Saati
  • Consultant : Abbas Al Saati
  • Project cost : 1 million
  • Position : Project Engineer.

9. 1997-1988

  • Project : Refurbishment works to MS Villa at Adliya
  • Client : Mr. Mohammed Salahuddin
  • Consultant : MSCEB
  • Position : Project Engineer.

10. 1996 -1997

  • Project : 3 Storey Building at Manama
  • Client : Ms.. Lulwa Jalal
  • Consultant : MSCEB
  • Position : Project Engineer

11. 1988 -1996

  • Entrusted various commercial and residential building in Kingdom of Bahrain
  • Position: Ste Engineer

12. 1984 -1988

  • Entrusted various building construction, Tunnel works etc., in Kerala India
  • Position: Site Engineer


Education

Graduation - Civcil Engineering

The Institution of Engineers India (IEI )
Kolkata/ India
09.2009 - 09.2015

Administrative Member of Indian Engineers (AMIE ) - Civil Engineering

The Institution of Engineers India ( I E I )
Kolkata / India
09.2015 - 09.2015

Chartered Civil Engineer Certificate - Civil Engineering

The Institution of Engineers India ( IEI )
Kolkata/ India
04.2016 - 04.2016

Skills

  • MS Word
  • Excel
  • PowerPoint
  • Auto Cad
  • Primavera
  • MS Project
  • Project Management
  • Leadership
  • Strategy
  • Motivation
  • Co-ordination
  • Issue Resolution
  • Meeting Arrangement
  • Minutes Preparation
  • Positive Attitude
  • Communication Skills
  • Time Management
  • Budget Management

Languages

English
Hindi

Custom

I now declare that the above information is true and correct to the best of my knowledge and belief.

Personal Information

  • Date of birth: 05/04/65
  • Nationality: Indian
  • Marital status: Married
  • Holding Bahrain & Indian Driving License.

Timeline

Projects Manager

Tamcon Contracting Company
08.2022 - Current

Chartered Civil Engineer Certificate - Civil Engineering

The Institution of Engineers India ( IEI )
04.2016 - 04.2016

Administrative Member of Indian Engineers (AMIE ) - Civil Engineering

The Institution of Engineers India ( I E I )
09.2015 - 09.2015

Graduation - Civcil Engineering

The Institution of Engineers India (IEI )
09.2009 - 09.2015

Projects Manager

Mohammed Jalal Contracting Company
01.2006 - 01.2022

Project Engineer, Site Manager

Hameed Alnooh Constructions
01.1988 - 01.2006
MOHANAN K PCivil Engineer